Pareto chart

A Pareto chart is a bar chart ordered from most frequent to least frequent, with a cumulative percentage line on a second axis. It applies the 80/20 rule (Pareto principle): roughly 80% of problems come from 20% of causes. The chart makes the “vital few” causes visible at a glance.

How to build a Pareto chart

  1. Count the frequency of each defect type or category.
  2. Sort categories from highest to lowest frequency.
  3. Calculate the total.
  4. Calculate cumulative frequency and cumulative percentage for each bar.
  5. Draw bars (left axis = count) and a cumulative line (right axis = %).

Worked example

A paint line logs defects over one month:

Defect typeCountCumulative countCumulative %
Scratches424250.0 %
Dents1860(42 + 18) / 84 = 0.7143 ≈ 71.4 %
Cracks1272(42 + 18 + 12) / 84 = 0.8571 ≈ 85.7 %
Voids77994.0 %
Other584100.0 %

Total defects = 84. Scratches and dents together account for 71.4% of all defects. A team that eliminates just two root causes—scratches and dents—would expect a 71% reduction in defect count. That is the power of the Pareto approach.

Practice problem

Five failure codes: A=30, B=12, C=8, D=6, E=4. Total=60. What cumulative percentage do A and B represent together?

Show answer

(30+12)/60 = 42/60 = 70.0%.

Common exam traps

Test yourself in 2 minutes

Try 5 free CQE practice questions on this exact topic. Every wrong answer comes with an explanation. No account needed.

Take the free CQE quiz

More: 5 Whys · 8D problem solving · AOQ & AOQL · APQP & PPAP · AQL sampling plans · Attribute agreement & kappa · Attribute control charts · Availability & maintainability · Benchmarking types · Binomial vs Poisson · Blocking & randomization · Calibration & traceability · Capability: non-normal · Chi-square test · Confidence intervals · Control chart selection · Control plan · CA effectiveness · Cost of quality · Cp vs Cpk vs Cpm · Cpk vs Ppk · CQE exam day tips · CQE study plan · CQE vs CQA vs CSSBB · Is the CQE worth it? · CUSUM & EWMA · Design reviews · Design V&V · Destructive testing · DFMEA vs PFMEA · Document control · Fault tree analysis · First article inspection · Fishbone diagram · FMEA: RPN vs AP · Full vs fractional factorial · Gage R&R · GD&T basics · Hazard vs risk vs harm · Hypothesis test selection · I-MR chart · Interaction plots · ISO 14971 · ISO 9001 clauses · Kaizen event planning · Kano model · Lean wastes (TIMWOODS) · Linear regression · Management review · MRB dispositions · MSA: bias, linearity & stability · NCR, CAPA & PA · Nonparametric tests · Normal distribution & z-table · One-way ANOVA · p-value explained · Pareto chart · PDCA vs DMAIC · Poka-yoke · QFD / House of Quality · Quality audits · Quality mgmt principles · Quality manual vs procedures · Quality plan vs control plan · Redundancy: parallel & standby · Reliability allocation · Bathtub curve & MTBF · Response surface methods · Risk-based thinking · Risk matrix vs FMEA · 7 mgmt & planning tools · Short-run SPC · Six Sigma certifications · Sigma level & DPMO · Six Sigma DMAIC · Supplier quality scorecards · Switching rules (sampling) · Taguchi loss function · Theory of constraints · Tolerance stackup · Traceability & lot control · Type I vs II error · Value stream mapping · Variables vs attributes · Weibull analysis · Western Electric rules · X-bar R vs X-bar S · CQE calculators · Study planner · Section quiz