APQP and PPAP explained

APQP (Advanced Product Quality Planning) is a structured process for developing new products and processes. It ensures quality is designed in from the start rather than inspected in at the end. APQP is an AIAG standard used across automotive supply chains and widely adopted in medical devices, aerospace, and other regulated industries.

PPAP (Production Part Approval Process) is the formal submission a supplier makes to a customer to prove that the production process can consistently produce parts meeting all requirements. PPAP is the deliverable at the end of APQP.

The five phases of APQP

PhaseWhat happensKey outputs
1. Plan and defineCapture voice of the customer; define design goalsDesign goals, reliability goals, preliminary BOM, preliminary process flow
2. Product design and developmentDesign the product; build and test prototypesDFMEA, design verification plan, engineering drawings, prototype build
3. Process design and developmentDesign the manufacturing processPFMEA, process flow diagram, control plan (pre-launch), MSA plan, floor plan
4. Product and process validationRun the production trial; validate that the process produces good partsProduction trial run, MSA studies, initial process capability (Ppk), PPAP submission
5. Feedback, assessment, and corrective actionLaunch support; track and reduce variationReduced variation, customer satisfaction data, lessons-learned documentation

The 18 PPAP elements

A PPAP submission typically contains up to 18 elements. The submission level (1–5) determines which elements the customer requires. Level 3 (most common) requires all elements plus a PSW (Part Submission Warrant) with sample parts.

Key elements: design documentation, DFMEA, process flow, PFMEA, control plan, measurement system analysis (MSA), dimensional results, material/performance test results, initial process capability (Ppk ≥ 1.67 for critical characteristics), initial sample inspection report, sample production parts, master sample, checking aids, customer-specific requirements, PSW.

Common exam traps

Practice problem

A supplier submits a PPAP with Cpk = 1.75 for a critical dimension. The customer rejects the submission. Why might this be legitimate?

Show answer

PPAP initial capability studies must use Ppk (overall standard deviation from the entire trial run), not Cpk (within-subgroup, short-term). Cpk can overstate true capability by ignoring between-subgroup variation. Most AIAG requirements set Ppk ≥ 1.67 for critical characteristics on a Level 3 or higher submission.

Test yourself in 2 minutes

Try 5 free CQE practice questions on this exact topic. Every wrong answer comes with an explanation. No account needed.

Take the free CQE quiz

More: 5 Whys · 8D problem solving · AOQ & AOQL · APQP & PPAP · AQL sampling plans · Attribute agreement & kappa · Attribute control charts · Availability & maintainability · Benchmarking types · Binomial vs Poisson · Blocking & randomization · Calibration & traceability · Capability: non-normal · Chi-square test · Confidence intervals · Control chart selection · Control plan · CA effectiveness · Cost of quality · Cp vs Cpk vs Cpm · Cpk vs Ppk · CQE exam day tips · CQE study plan · CQE vs CQA vs CSSBB · Is the CQE worth it? · CUSUM & EWMA · Design reviews · Design V&V · Destructive testing · DFMEA vs PFMEA · Document control · Fault tree analysis · First article inspection · Fishbone diagram · FMEA: RPN vs AP · Full vs fractional factorial · Gage R&R · GD&T basics · Hazard vs risk vs harm · Hypothesis test selection · I-MR chart · Interaction plots · ISO 14971 · ISO 9001 clauses · Kaizen event planning · Kano model · Lean wastes (TIMWOODS) · Linear regression · Management review · MRB dispositions · MSA: bias, linearity & stability · NCR, CAPA & PA · Nonparametric tests · Normal distribution & z-table · One-way ANOVA · p-value explained · Pareto chart · PDCA vs DMAIC · Poka-yoke · QFD / House of Quality · Quality audits · Quality mgmt principles · Quality manual vs procedures · Quality plan vs control plan · Redundancy: parallel & standby · Reliability allocation · Bathtub curve & MTBF · Response surface methods · Risk-based thinking · Risk matrix vs FMEA · 7 mgmt & planning tools · Short-run SPC · Six Sigma certifications · Sigma level & DPMO · Six Sigma DMAIC · Supplier quality scorecards · Switching rules (sampling) · Taguchi loss function · Theory of constraints · Tolerance stackup · Traceability & lot control · Type I vs II error · Value stream mapping · Variables vs attributes · Weibull analysis · Western Electric rules · X-bar R vs X-bar S · CQE calculators · Study planner · Section quiz