Control plan explained
A control plan is a written summary of the control methods used to maintain process performance and product quality. It tells operators and inspectors what to check, how to check it, how often, and what to do when something is out of control.
The control plan is not a list of specifications—it is a living operations document. It references the process flow and PFMEA and is updated whenever the process changes.
Key columns in an AIAG control plan
| Column | What it captures |
|---|---|
| Part / process name | The step or component being controlled |
| Characteristic number | Links back to the drawing or PFMEA item |
| Product / process characteristic | The specific dimension, attribute, or parameter being controlled |
| Special characteristic | Flagged with symbols (e.g., △ for safety, ◆ for key product characteristic) |
| Specification / tolerance | The acceptance limit (from the drawing or standard) |
| Evaluation measurement technique | Gage, fixture, test method, visual standard |
| Sample size and frequency | How many parts and how often to check |
| Control method | SPC chart, attribute chart, go/no-go gage, 100% inspection |
| Reaction plan | What the operator must do when the characteristic is out of control (contain, tag, call supervisor, stop production) |
Three types of control plan
- Prototype control plan: covers prototype builds in APQP Phase 2. Less formal; focus is on development learning.
- Pre-launch control plan: used during the production trial run (APQP Phase 4). More rigorous; all characteristics identified.
- Production control plan: the live document used every day on the shop floor. Updated when process or design changes occur.
Common exam traps
- The reaction plan is not optional. Every controlled characteristic needs a documented reaction plan. “Stop and call supervisor” is a valid reaction plan; blank is not.
- Control plans do not replace work instructions. A control plan says what to control; a work instruction says how to do the operation. They are complementary.
- Special characteristics always appear in the control plan. Any characteristic flagged in the DFMEA or PFMEA as safety-critical or key must appear in the control plan with an appropriate control method.
- The control plan is updated after every change. Process change approval is not complete until the control plan reflects the new state.
Try 5 free CQE practice questions on this exact topic. Every wrong answer comes with an explanation. No account needed.
Take the free CQE quizMore: 5 Whys · 8D problem solving · AOQ & AOQL · APQP & PPAP · AQL sampling plans · Attribute agreement & kappa · Attribute control charts · Availability & maintainability · Benchmarking types · Binomial vs Poisson · Blocking & randomization · Calibration & traceability · Capability: non-normal · Chi-square test · Confidence intervals · Control chart selection · Control plan · CA effectiveness · Cost of quality · Cp vs Cpk vs Cpm · Cpk vs Ppk · CQE exam day tips · CQE study plan · CQE vs CQA vs CSSBB · Is the CQE worth it? · CUSUM & EWMA · Design reviews · Design V&V · Destructive testing · DFMEA vs PFMEA · Document control · Fault tree analysis · First article inspection · Fishbone diagram · FMEA: RPN vs AP · Full vs fractional factorial · Gage R&R · GD&T basics · Hazard vs risk vs harm · Hypothesis test selection · I-MR chart · Interaction plots · ISO 14971 · ISO 9001 clauses · Kaizen event planning · Kano model · Lean wastes (TIMWOODS) · Linear regression · Management review · MRB dispositions · MSA: bias, linearity & stability · NCR, CAPA & PA · Nonparametric tests · Normal distribution & z-table · One-way ANOVA · p-value explained · Pareto chart · PDCA vs DMAIC · Poka-yoke · QFD / House of Quality · Quality audits · Quality mgmt principles · Quality manual vs procedures · Quality plan vs control plan · Redundancy: parallel & standby · Reliability allocation · Bathtub curve & MTBF · Response surface methods · Risk-based thinking · Risk matrix vs FMEA · 7 mgmt & planning tools · Short-run SPC · Six Sigma certifications · Sigma level & DPMO · Six Sigma DMAIC · Supplier quality scorecards · Switching rules (sampling) · Taguchi loss function · Theory of constraints · Tolerance stackup · Traceability & lot control · Type I vs II error · Value stream mapping · Variables vs attributes · Weibull analysis · Western Electric rules · X-bar R vs X-bar S · CQE calculators · Study planner · Section quiz