Short answer: both are ways to decide which failure modes to work on first. The RPN multiplies three ratings: Severity ร— Occurrence ร— Detection, each scored 1โ€“10. Action Priority (AP), used in the newer AIAG-VDA FMEA approach, puts each S-O-D combination into High, Medium or Low priority with a lookup table that gives the most weight to severity, then occurrence, then detection.

Why RPN can mislead

Multiplication treats the three ratings as equally important, and very different risks can get the same score. A safety failure that rarely happens can score lower than a cosmetic defect that happens often.

Worked example

Failure modeSODRPN
A: brake line fitting cracks92354
B: label printed off-center366108
RPN A = 9 ร— 2 ร— 3 = 54 RPN B = 3 ร— 6 ร— 6 = 108

What it means: rank by RPN and you'd fix the label first. Almost any team would want the brake fitting reviewed first, though, because a severity of 9 means a safety or regulatory effect. Severity-first logic like AP puts A ahead of B. Whichever method your organization uses, also apply a severity rule: any 9 or 10 gets a look no matter what the other ratings are.

How to lower the risk

Common exam traps

Test yourself in 2 minutes

Try 5 free CQE practice questions, including a calculation problem with fresh numbers. Every wrong answer comes with an explanation. No account needed.

Take the free CQE quiz

More: 5 Whys · 8D problem solving · AOQ & AOQL · APQP & PPAP · AQL sampling plans · Attribute agreement & kappa · Attribute control charts · Availability & maintainability · Benchmarking types · Binomial vs Poisson · Blocking & randomization · Calibration & traceability · Capability: non-normal · Chi-square test · Confidence intervals · Control chart selection · Control plan · CA effectiveness · Cost of quality · Cp vs Cpk vs Cpm · Cpk vs Ppk · CQE exam day tips · CQE study plan · CQE vs CQA vs CSSBB · Is the CQE worth it? · CUSUM & EWMA · Design reviews · Design V&V · Destructive testing · DFMEA vs PFMEA · Document control · Fault tree analysis · First article inspection · Fishbone diagram · FMEA: RPN vs AP · Full vs fractional factorial · Gage R&R · GD&T basics · Hazard vs risk vs harm · Hypothesis test selection · I-MR chart · Interaction plots · ISO 14971 · ISO 9001 clauses · Kaizen event planning · Kano model · Lean wastes (TIMWOODS) · Linear regression · Management review · MRB dispositions · MSA: bias, linearity & stability · NCR, CAPA & PA · Nonparametric tests · Normal distribution & z-table · One-way ANOVA · p-value explained · Pareto chart · PDCA vs DMAIC · Poka-yoke · QFD / House of Quality · Quality audits · Quality mgmt principles · Quality manual vs procedures · Quality plan vs control plan · Redundancy: parallel & standby · Reliability allocation · Bathtub curve & MTBF · Response surface methods · Risk-based thinking · Risk matrix vs FMEA · 7 mgmt & planning tools · Short-run SPC · Six Sigma certifications · Sigma level & DPMO · Six Sigma DMAIC · Supplier quality scorecards · Switching rules (sampling) · Taguchi loss function · Theory of constraints · Tolerance stackup · Traceability & lot control · Type I vs II error · Value stream mapping · Variables vs attributes · Weibull analysis · Western Electric rules · X-bar R vs X-bar S · CQE calculators · Study planner · Section quiz

CQE Quest by Bizarre Act. Original study material; not affiliated with ASQ. CQE is a certification of ASQ. Terms ยท Privacy