Six Sigma project charter

The project charter is the Define phase’s primary deliverable. It is a one-page (or short) contract between the project team and the sponsoring organization that answers six questions: why, what, how bad, how much better, for whom, and by when. A weak charter (vague problem, unmeasurable goal, unbounded scope) is a frequent root cause of stalled or failed Six Sigma projects.

Six charter elements

ElementWhat it must containCommon mistake
Business caseWhy this project matters to the organization: financial impact, strategic alignment, customer riskToo vague (“important to quality”); no dollar figure
Problem statementWhat is wrong, where it occurs, how often, and since when — no causes, no solutionsEmbedding the cause (“operators aren’t following the procedure”) or solution (“we will implement a new system”)
Goal statementSpecific, Measurable, Achievable, Relevant, Time-bound (SMART) improvement targetSaying “improve” or “reduce” without a number or deadline
Project scopeClear in-scope and out-of-scope boundaries (start and stop of the process, product lines, sites)Scope so wide the team can’t finish in 6 months; or so narrow it can’t achieve the business case
TeamBlack Belt, Champion, process owner, subject-matter experts, Finance rep (for savings validation)Missing a Finance or process-owner sign-off
TimelineTollgate dates for each DMAIC phase, final completion dateNo dates or unrealistic compression

Worked example charter

Project: Reduce tablet coating defect rate at ZZPharma Line 4

Business case: Coating defects on Line 4 cause ~$420,000/yr in rework and scrapped batches. Line 4 accounts for 40% of site output. Customer complaints about appearance have increased 3× over the past 18 months.

Problem statement: The coating defect rate on ZZPharma Line 4 averaged 4.7% over the past 12 months (Oct 2024–Sep 2025), measured as percentage of tablets requiring rework or scrap at final visual inspection. The target specification is ≤1.0%.

Goal statement: Reduce the Line 4 coating defect rate from 4.7% to ≤1.5% by June 30, 2026, saving at least $280,000/yr in rework and scrap costs (≈ $420,000 × (4.7 − 1.5)/4.7, assuming cost scales with defect rate).

Scope: In scope: coating pan loading through in-process visual inspection on Line 4. Out of scope: tablet compression, packaging, and Lines 1–3.

Team: Black Belt: J. Exampl; Champion: VP Operations; Process owner: Line 4 supervisor; Finance: Cost accounting rep

Timeline: Define – Nov 30 · Measure – Jan 15 · Analyze – Feb 28 · Improve – Apr 30 · Control – Jun 30

Problem statement rules

A valid problem statement is factual, specific, and solution-neutral. Test yours against these:

Common exam traps

Test yourself in 2 minutes

Try 5 free CSSBB practice questions on project charters and Define tollgate deliverables.

Take the free CSSBB diagnostic

More: DMAIC overview · Project charter · VOC & CTQ · SIPOC · MSA in DMAIC · Process capability · Data collection planning · Graphical analysis · Root cause analysis · Multi-vari analysis · Hypothesis testing · Regression · DOE · FMEA · Define tollgate · Change management · Financial benefits · Team dynamics · Improve tollgate · Piloting & scaling · Poka-yoke (BB) · Solution selection · Control plan · SPC in DMAIC · Sustaining gains

CSSBB Quest by Bizarre Act. Original study material; not affiliated with ASQ. CSSBB is a certification of ASQ. Terms · Privacy