🏭 CSSGB Quest › Section VI

Section VI: Control Phase 15 questions

Control carries 15 of the 100 scored questions on the 2022 CSSGB exam (up from 11 in the 2014 BoK). It covers statistical process control, the control plan, and the lean tools that keep a process in control: total productive maintenance (TPM) and the visual factory.

Key topics

TopicWhat to know
SPC basicsCommon vs. special cause variation; measuring and monitoring process performance for continuous and discrete data.
Rational subgroupingForm subgroups from units made under essentially the same conditions, so within-subgroup variation is common cause only.
Control chartsSelecting, building and interpreting I-MR, X̄-R, X̄-s, p, np, c and u charts; run rules for out-of-control signals.
Control planWhat is monitored, how, how often, by whom, and the reaction plan when a signal or out-of-spec result occurs; handoff to the process owner.
TPMOperator-involved maintenance to prevent breakdowns; overall equipment effectiveness (OEE).
Visual factoryAndon lights, shadow boards, floor markings, kanban and status boards that make abnormal conditions obvious.

Control chart selection

DataChart
Continuous, individual readings (n = 1)I-MR
Continuous, small subgroups (typically n = 2–9)X̄-R
Continuous, larger subgroups (typically n ≥ 10)X̄-s
Proportion defective (constant or varying n)p
Number defective, constant nnp
Count of defects, constant area of opportunityc
Defects per unit, varying area of opportunityu

Run rules

A chart can signal a special cause even when every point is inside the 3σ limits. The Western Electric rules:

  1. 1 point beyond 3σ
  2. 2 of 3 consecutive points beyond 2σ on the same side
  3. 4 of 5 consecutive points beyond 1σ on the same side
  4. 8 consecutive points on one side of the center line

The Nelson rules, used in many software packages, use 9 points on one side instead of 8 and add trends (6 points steadily rising or falling) and other patterns. Use whichever set the question names.

OEE (TPM)

OEE = Availability × Performance × Quality
  0.90 × 0.95 × 0.99 = 0.846  (84.6%)

Reaction plans

A complete reaction plan says who acts when a signal occurs, the immediate containment (stop, hold or segregate product, escalate), and how the cause is investigated and corrected. "Notify the supervisor" alone is incomplete.

Common exam traps

Learn pages for this section

Control chartsSelection, limits, rules Control plan & handoffReaction plan Run chartsCommon vs. special cause
Test your Section VI knowledge

The free 20-question CSSGB diagnostic covers all six sections and shows your score by section.

Take the free diagnostic →

Section names and question counts follow the 2022 CSSGB Body of Knowledge (110 questions, 100 scored). Topic summaries are our paraphrase; check the current BoK on asq.org for the official wording.

I II III IV V VI

CSSGB Quest by Bizarre Act. Original study material; not affiliated with ASQ. CSSGB is a certification of ASQ. Terms · Privacy