Mistake-proofing (poka-yoke)

Poka-yoke means “mistake-proofing” in Japanese. It is a device or design feature that prevents an error from occurring or immediately detects it if it does. Green Belt exams test the difference between prevention and detection poka-yokes, the levels of robustness, and common workplace examples.

Prevention vs. detection

TypeWhat it doesPreferred?Example
PreventionPhysically or mechanically stops the error from being made or from proceedingYes — strongerA USB connector that can only insert one way; a jig that won’t clamp unless the part is correctly oriented
DetectionDetects the error after it has occurred and signals or stops the processSecond choiceA sensor that triggers an alarm when a lid is not seated; a vision system that rejects a misassembled unit

Levels of poka-yoke (strongest to weakest)

  1. Elimination: Redesign so the error is physically impossible. The most robust level. Example: redesigning a two-piece assembly into one molded part so the assembly step (and its errors) no longer exists.
  2. Prevention: A physical feature stops the error or prevents the process from continuing after one. Example: a machine that locks if a safety guard is open.
  3. Detection: The error is detected and the product is stopped or rejected before reaching the next step. Example: a weight check that diverts underweight units.
  4. Warning: An alarm or indicator notifies the operator that an error has occurred or is about to. The weakest form — relies on human response. Example: a beep when a door is ajar.

Common mistake types and poka-yoke approaches

Mistake typeExamplePoka-yoke approach
Wrong orientationPart inserted upside-downAsymmetric shape; locating pin that prevents wrong orientation
Missing stepOperator skips a process stepChecklists with mandatory electronic sign-off; sequence interlock that prevents step N+1 until step N is confirmed
Wrong partIncorrect component usedKanban kitting that delivers the right part only; barcode scan that must match before proceeding
Quantity errorToo few fasteners installedCounted kitting trays; torque tools that count cycles before releasing
Measurement errorIncorrect dimension set on machineDigital readout with set-point lock; go/no-go gauge

Exam tip

When a question asks the Green Belt to “mistake-proof the process,” the correct answer is almost always a prevention or elimination approach, not additional inspection. Inspection is a detection control, which is better than nothing but inferior to preventing the error from occurring.

Test yourself

The free 20-question CSSGB diagnostic covers all six Body of Knowledge sections, with an explanation for every answer.

Take the free CSSGB diagnostic

Related: Solution selection · Waste identification · Control plan

CSSGB Quest by Bizarre Act. Original study material; not affiliated with ASQ. CSSGB is a certification of ASQ. Terms · Privacy