Takt time

Takt time is the maximum time allowed to produce one unit in order to meet customer demand. It translates customer pull into a production pace. “Takt” is German for beat or pulse (as in a conductor’s beat) — it sets the rhythm of production.

Formula

Takt time = Available production time ÷ Customer demand rate

Both must use the same time unit (minutes per unit, seconds per unit, etc.)

Worked example

Setup:
Shift time: 480 minutes/day
Breaks and lunch: 50 minutes/day
Available time: 480 − 50 = 430 minutes/day
Customer demand: 86 units/day

Takt time = 430 ÷ 86 = 5 minutes per unit

The process must complete one unit every 5 minutes to meet demand without overproducing.

Interpreting takt time vs. cycle time

How takt time guides the Improve phase

In a DMAIC Improve phase, takt time tells the Green Belt the target cycle time for each process step. A value stream map overlaid with takt time immediately shows which steps exceed takt (bottlenecks) and which are well under it (candidates for load balancing or combining). The Improve goal is to bring all steps to at or below takt time without creating overproduction upstream.

Common exam traps

Test yourself

The free 20-question CSSGB diagnostic covers all six Body of Knowledge sections, with an explanation for every answer.

Take the free CSSGB diagnostic

Related: Value stream mapping · Waste identification · 5S

CSSGB Quest by Bizarre Act. Original study material; not affiliated with ASQ. CSSGB is a certification of ASQ. Terms · Privacy